A site report written by me earlier this week.
Steve,
Please find listed below the issues discussed and agreements reached with ---- ------- yesterday (11-03-10)
RAMS
1.0 - Risk assessment and method statement issued for approval rejected!
1.1 - Method statement to be re-issued taking main contractors recommendations into account.
DELIVERIES
2.0 - Procedures discussed and agreement reached.
2.1 - All deliveries to be accepted and unloaded as specified in method statement.
2.2 - Main contractor to be given a minimum 24 hours notice whenever possible.
2.3 - Delivery schedule to be issued to the main contractor whenever possible.
2.4 – Delivery slot each week, on the same day and at the same time would be beneficial.
GENERAL
3.0- Assurances were given that plant deck floor plinths would be completed by 22/4/10. Deliveries of dampers and ductwork have been arranged accordingly.
3.1- Plant level loading bay scaffold will need to be adapted.
3.2- Some plasterboard walls will need to be erected before the majority of plantroom ductwork can be installed. This will need to happen alongside the 1st floor ductwork plasterboard wall installation.
3.3 - Assurances were given that the 1st floor ductwork installation would be able to commence 07/04/10. Deliveries of dampers and ductwork have been arranged accordingly.
3.4- Not all, but many, plasterboard walls will need to be erected before any specific area can be deemed ready for ductwork installation.
Kind regards
Brian
Can anybody help me improve on this. On reflection I am not really happy with the format or content.