Dear All,
Please find time to edit my draft minutes below. Anticipating
for your quick reply. Many thanks.
__________________________________________________ ____________
Minutes of Meeting
July 10, 2010
Office Conference Room, ABC Building, DEF Dist., Jeddah
This meeting was held last July 10, 2010 at
the Office Conference Room, ABC Building, Jeddah. It was presided by Engr. L.
I. Attendees.
The following were present at the meeting:
1. Engr. D - Construction Manager
2. Engr. E - Projects Manager
3. Mr. F - Finance Manager
4. Mr. G - Chief Accountant
5. Engr. H - Project Manager
6. Engr. I - In – Charge, Plumbing & FFW
7. Engr. J - Department Head, Electrical
8. Engr. K - Department Head, Structural
9. Engr. L - QMR/Senior Quality Engineer
10. Engr. M - Department Head, HR
11. Engr. N - Project Manager
12. Mr. O - Department Head, Purchasing
13. Mr. Q - Secretary
II. Discussion.
1. The meeting
proper was called
into to order at 3:05 PM. Engr. L extended his thanks and acknowledgement to all present for attending this brief meeting. This meeting has been purposely called in connection
for with the upcoming pre-assessment audit of the company on Monday, 12 July 2010
who that will be conducted by the SGS Group. Engr. L cited the following items as the scope of the pre-assessment, namely,
(i.)Quality Policy
(ii.)Quality Objectives
(iii.)Management Responsibilities/Commitment
(iv.)Quality Procedures
(v.) Record Management
The abovementioned items are also requisites in securing
the ISO Certificate. Engr. L
had further reminded all
managers and
department
heads present to fully understand the above concepts. Pre-assessment will be done through physical inspections of each
department. During pre-assessment each
Managers manager and
department
Heads head might be asked
, in relation of each scope of work, how quality policy, quality objectives, management responsibilities, quality procedures and records’ management are being implemented; hence, everyone is advised to answer the questions precisely. The results of this pre-assessment would be a basis of the actual assessment
proper and the findings of it would also be the references of the things that the company should revise and comply.
2. Engr. J commented on one of the quality objectives that says “
reduce cost of non-conforming materials (scrap and rework) by 10%” which for him is non–achievable. He added that in the construction, included in the costing and estimation
, is
the an anticipated 5% waste of materials. 10% is quite big. Further, he suggested that this statement be revised implying non–confirming materials be reduced TO 10% and not BY 10%.
3. Engr. D stressed that non-conforming materials is 0%
, since all materials to be purchased are thoroughly examined and ensured that these are all conformed on the certain project and have been passed for approval from the project and construction managers and consultants.
4. Engr. L said this has something to do with the quality management wherein there is a need to check, plan, do and act (PDA)
, and using the Root Cause Analysis (RCA) concept.
5. Engr. I suggested to
well first define
first the terminologies/phrases – scope of these non-confirming materials, scrap and reworks by 10%.
6. Mr. F suggested that since these have not yet been submitted to the
auditors, this statement should
be reword
ed or rephrase
d.
7. All present agreed
to the suggestion.
8. Engr. L requested
to give him ample time to restate the said line.
What is the "said line"?
9. Engr. E asked how these non–confirming materials
can be applied to other departments such as in HR, Purchasing and Accounting. He further suggested that Engr. Rivera
will draft possible questions that would be coming out during the pre-assessment.
10. Engr. L answered that drafting possible questions is not necessary as long as one knows each job and understands all
these of the company
's quality policies, objectives and management. He briefly discussed that in the quality procedure this includes the functions of every department head and
each all personnel. Records’ Management pertains to the traceability and easy tracking of all files; hence labeling is needed. Engr. L reminded all to please find time to read the company manual.
11. Engr. J asked a copy of the manual; Engr. Rivera replied
that he would he’ll give him one.
12. Engr. E commented that the
said meeting
is was fruitful and interactive where everybody
is was concerned and
has shown showed an interest in securing
the ISO Certificate
en shallah. What is the meaning of en shallah? III. Adjournment.
Meeting adjourned at 4:05 PM.
Attachment: Attendance
Minutes were taken by:
Mr. Q
Secretary
NOTED BY: Engr. L
QMR/Senior Quality Engineer
Engr. R
General Manager/Owner